TextureSync

Company: AI4 - HS Offenburg
Manager: Hendrik Schutter
Start: March 22, 2019
Finish: January 1, 1970
Report Date: January 1, 1970

Gantt Chart

WBS Name Work
     
1 Definition 10d
1.1 Charta [M] 1d
1.2 Lastenheft [M] 3d
1.3 Pflichtenheft [M] 3d
1.4 Risikoanalyse [M] 3d
2 Plannung 23d
2.1 Grobdesign [M] 3d
2.1.1 Architektur festlegen 3d
2.2 Feindesign [M] 16d
2.2.1 3D Test auf Kotlin + ChipView Test 3d
2.2.2 Netzwerk-Protokoll definieren 3d
2.2.3 Mockups 2d
2.2.4 Wie Metadaten filtern? 2d
2.2.5 Datenerhaltung 3d
2.2.6 UI Elemente beschreiben 3d
2.3 Task zuweisen 1d
2.4 Mastertestplan [M] 3d
3 End of Design
4 Realisation 37d
4.1 Einrichtung von Tests 1d
4.1.1 Client Tests 1d
4.2 Client 19d
4.2.1 UI 10d
4.2.1.1 Previews 3d
4.2.1.2 Filter UI 3d
4.2.1.3 3D Visualisierung 2d
4.2.1.4 Dateien hinzufügen 1d
4.2.1.5 Dateien lokal abspeichern 1d
4.2.2 Grund Architektur 3d
4.2.3 Protokoll implementieren 6d
4.3 Server 17d
4.3.1 Dateien speichern/verwalten 6d
4.3.2 Protokoll implementieren 6d
4.3.3 Suche implementieren 3d
4.3.4 Hauptlogik implementieren 2d
5 End of Implementation
6 Abnahme 13d
6.1 Modultests [M] 4d
6.2 Integrationstests [M] 4d
6.3 Systemtests [M] 4d
6.4 Akzeptanztest [M] 1d
Week 13, 2019 Week 14, 2019 Week 15, 2019 Week 16, 2019 Week 17, 2019 Week 18, 2019 Week 19, 2019 Week 20, 2019 Week 21, 2019 Week 22, 2019 Week 23, 2019 Week 24, 2019
22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
L
R[50], H[50]
R, H[10], L[80]
J
R
J
R
L
J
H
H[50], J[50]
R

Tasks

WBS Name Start Finish Work Complete Cost Assigned to Notes
1 Definition Mar 23 Apr 3 10d
1.1 Charta [M] Mar 23 Mar 23 1d 100%
1.2 Lastenheft [M] Mar 23 Mar 27 3d 100%
1.3 Pflichtenheft [M] Mar 30 Apr 3 3d 100% L
1.4 Risikoanalyse [M] Mar 30 Apr 3 3d 100% R[50], H[50]
2 Plannung Apr 6 Apr 20 23d
2.1 Grobdesign [M] Apr 6 Apr 9 3d
2.1.1 Architektur festlegen Apr 6 Apr 9 3d 100% R, H[10], L[80]
2.2 Feindesign [M] Apr 9 Apr 20 16d
2.2.1 3D Test auf Kotlin + ChipView Test Apr 9 Apr 16 3d 100% J
2.2.2 Netzwerk-Protokoll definieren Apr 9 Apr 16 3d 100% R
2.2.3 Mockups Apr 9 Apr 13 2d 100% J
2.2.4 Wie Metadaten filtern? Apr 17 Apr 20 2d 100% R
2.2.5 Datenerhaltung Apr 9 Apr 16 3d 100% L
2.2.6 UI Elemente beschreiben Apr 9 Apr 16 3d 100% J
2.3 Task zuweisen Apr 9 Apr 10 1d 100%
2.4 Mastertestplan [M] Apr 9 Apr 16 3d 100% H
3 End of Design Apr 16 Apr 16
4 Realisation Apr 23 May 11 37d
4.1 Einrichtung von Tests Apr 23 Apr 23 1d
4.1.1 Client Tests Apr 23 Apr 23 1d 0%
4.2 Client Apr 23 May 4 19d
4.2.1 UI Apr 24 Apr 30 10d
4.2.1.1 Previews Apr 24 Apr 30 3d 0%
4.2.1.2 Filter UI Apr 24 Apr 30 3d 0%
4.2.1.3 3D Visualisierung Apr 24 Apr 27 2d 50%
4.2.1.4 Dateien hinzufügen Apr 24 Apr 24 1d 0%
4.2.1.5 Dateien lokal abspeichern Apr 24 Apr 24 1d 0%
4.2.2 Grund Architektur Apr 23 Apr 27 3d 70% H[50], J[50]
4.2.3 Protokoll implementieren Apr 23 May 4 6d 0%
4.3 Server Apr 23 May 11 17d
4.3.1 Dateien speichern/verwalten Apr 23 May 4 6d 100%
4.3.2 Protokoll implementieren Apr 23 May 4 6d 100% R
4.3.3 Suche implementieren May 7 May 11 3d 100%
4.3.4 Hauptlogik implementieren May 7 May 8 2d 100% Hauptsächlich Glue-Code
5 End of Implementation May 11 May 11
6 Abnahme May 14 Jun 11 13d
6.1 Modultests [M] May 14 May 21 4d 0%
6.2 Integrationstests [M] May 22 May 29 4d 0%
6.3 Systemtests [M] Jun 1 Jun 8 4d 0%
6.4 Akzeptanztest [M] Jun 11 Jun 11 1d 0%

Resources

Name Short name Type Group Email Cost
Hendrik H Work 0
Jannik J Work 0
Lukas L Work 0
Robin R Work 0